Fishbourne residents are being warned of noise as Wightlink carries out 'essential maintenance'.
The ferry firm is undertaking work to its berth at Fishbourne port from next Monday (29) to Friday May 14, 2021.
Aging fenders will be replaced with new ones in four weeks of overnight work, scheduled to take place when tides permit.
Wightlink Chief Executive Keith Greenfield said:
"Our contractors will do their best to keep disturbance to a minimum but unfortunately, there may be some noise. We apologise in advance if this causes any inconvenience to our neighbours in Fishbourne.”
Contractors will be based on a barge offshore during the operation.
The replacement work will be suspended if winds rise over 25 knots.
Some sailings will be cancelled as a result of the works.
Schedule of fender works at Fishbourne
Monday 29 March – Friday 2 April |
Berthworks 20:00-05:00 |
Monday 5 April – Friday 9 April |
No works because of tides |
Monday 12 April – Friday 16 April |
Berthworks 20:00-05:00. The 23:00 and 01:00 sailings from Fishbourne will be cancelled on 13 and 14 April |
Monday 19 April – Friday 23 April |
No works because of tides |
Monday 26 April – Friday 30 April |
Berthworks 20:00-05:00 |
Monday 3 May – Friday 7 May |
No works because of tides |
Monday 10 May – Friday 14 May |
Berthworks 20:00-05:00. The 23:00 and 01:00 sailings from Fishbourne will be cancelled on 11 and 12 May |